Are Liquidated Damages Enforceable in Florida Contracts?
Florida’s business contracts often include a liquidated damages clause, a provision that sets a fixed dollar amount one party must pay if the contract is breached. Instead of calculating actual damages later, the parties agree on the amount upfront. While this can provide certainty, it also creates serious risks. Liquidated damages can expose businesses to large financial penalties that may exceed the real losses suffered, and many owners only realize the impact once they are facing a claim.
In Florida, courts will only enforce these clauses if two conditions are met: the damages were difficult to estimate at the time of contracting, and the amount chosen is a reasonable projection of potential loss. If the number looks more like punishment than compensation, it may be struck down as an unenforceable penalty.
The risks for business owners are clear:
- Paying steep damages that may not be enforceable under Florida law
- Losing leverage in disputes when the other side relies on the clause as written
- Facing financial strain that could have been avoided with proper legal review
At Southron Firm, P.A., we help Florida businesses understand when liquidated damages are valid and when they can be challenged. Our contract law attorneys have successfully defended clients against unfair penalties and protected their businesses from unnecessary losses.
Don’t wait until penalties threaten your business—speak with our contract attorneys today to protect your rights and limit your risk.
What are Liquidated Damages?
A liquidated damages clause is a contract provision that sets a fixed amount one party must pay if they fail to meet their obligations. Instead of calculating actual damages later in court, the parties agree in advance on a number that represents the likely harm. These clauses are common in Florida construction contracts, vendor agreements, and service contracts because they offer predictability when actual damages are hard to measure.
For example, a construction company in Tampa might agree to pay $2,000 per day if a project runs late, or a supplier in Orlando might face a $10,000 charge if delivery deadlines are missed. On the surface, this can simplify disputes. In reality, liquidated damages often become a point of conflict because the amounts are sometimes set too high, applied unfairly, or used as leverage against one side.
Key risks for Florida businesses include:
- Penalties that are higher than the actual losses caused
- Clauses written to favor only one party, leaving the other exposed
- Financial strain that can exceed the value of the entire contract
While liquidated damages can provide clarity, they also carry significant financial risks. A single clause buried in a contract can expose your business to losses that may not even be enforceable under Florida law.
Are Liquidated Damages Enforceable in Florida?
Whether liquidated damages hold up in court depends on how they are written. Florida courts enforce these provisions only if they are fair, proportionate, and tied to real business risks. If they operate as punishment, they are considered unenforceable penalties.
Florida law looks at three main factors:
- Uncertainty of damages: Were the actual damages difficult to estimate at the time the contract was signed?
- Reasonableness of the amount: Does the figure reasonably reflect the anticipated loss?
- Proportionality: Is there a fair relationship between the agreed damages and the likely harm?
This standard is well-established in Florida case law. In Lefemine v. Baron, 573 So. 2d 326 (Fla. 1991), the Florida Supreme Court ruled that when liquidated damages are “grossly disproportionate” to the actual harm, they cannot be enforced. In Secrist v. National Service Industries, Inc., 395 So. 2d 1280 (Fla. 2d DCA 1981), a clause was struck down because the damages bore no reasonable relation to the potential loss.
Contracts involving the sale of goods are also governed by Florida’s Uniform Commercial Code, specifically Fla. Stat. § 672.718(1), which allows liquidated damages only if the amount is “reasonable in light of the anticipated or actual harm.”
The takeaway for business owners: liquidated damages are not automatically valid just because they’re written in the contract. Courts will enforce them only if they are fair and reasonable. If the clause crosses into punishment, it fails.
Don’t assume a liquidated damages clause is enforceable. One unfair provision could cost your business thousands. Get legal guidance now before it’s too late.

Common Problems with Liquidated Damages
Many Florida businesses encounter unexpected challenges with liquidated damages clauses, especially when the language is unclear or the amounts are excessive. These provisions can create significant financial risk and lead to disputes that could have been avoided. Understanding the common pitfalls can help protect your business before a contract is signed.
Common problems with liquidated damages include:
- Excessive Penalties: Clauses that impose amounts far greater than any reasonable estimate of actual damages, creating unnecessary financial risk.
- One-Sided Terms: Provisions that favor only one party, often putting smaller businesses or subcontractors at a disadvantage.
- Vague or Overly Broad Language: Ambiguous wording can leave room for misinterpretation, disputes, or misuse.
These issues aren’t just theoretical. For instance, we’ve represented construction contractors in Tampa who faced daily fines so high that a single delay threatened to bankrupt the project. In another case, a vendor’s “late delivery” penalties exceeded the total value of the contract, leaving the client exposed to significant financial liability.
At Southron Firm, P.A., we help businesses identify these red flags, negotiate fairer terms, and defend against penalties that are unfair or unenforceable.
What To Do If You’re Facing Liquidated Damages
Liquidated damages clauses can create significant financial risk for Florida businesses if not handled carefully. Whether you’re being threatened with penalties or reviewing a contract that includes them, taking proactive steps is essential to protect your bottom line. Acting too late or without proper guidance can result in paying more than necessary—or being unfairly held liable. Knowing your rights and options under Florida law can make all the difference.
- Seek legal guidance before paying: Don’t assume the clause is enforceable. An experienced attorney can determine whether the damages are valid under Florida law.
- Document everything: Keep emails, notices, and records of delays or any factors that could affect responsibility for the alleged breach.
- Consult a contract lawyer: A skilled Florida business contract review attorney can review the agreement, explain your options, and help negotiate or challenge unfair penalties.
Taking the right steps early can prevent a small contractual issue from becoming a costly dispute. With proper legal guidance, you can protect your business, avoid unnecessary payments, and address liquidated damages claims with confidence.
How Our Contract Attorneys Can Help You Enforce Liquidated Damages
At Southron Firm, P.A., we help Florida businesses navigate the complex world of liquidated damages. Whether you are reviewing a new contract or facing a claim under an existing agreement, our attorneys ensure your rights and interests are protected. We provide practical, results-driven guidance to prevent unfair penalties and minimize financial risk.
When clients bring us contracts with liquidated damages clauses, we:
- Review enforceability under Florida law: We determine whether the clause is valid and what risks it poses to your business.
- Negotiate fairer terms before a contract is signed: Our attorneys work to adjust clauses that are overly harsh or one-sided.
- Defend businesses accused of breaching contracts: We protect you when another party tries to impose unfair penalties.
- Pursue claims for valid liquidated damages: If you are entitled to recover damages, we help ensure the other party meets their obligations.
We’ve successfully represented contractors, suppliers, and service providers across Florida protecting them from costly penalties and unfair contract terms. Our goal is simple: we protect Florida businesses from unfair contracts, excessive penalties, and damaging lawsuits.
Whether you need a contract reviewed before signing or legal representation against a liquidated damages claim, Southron Firm, P.A. is ready to step in and safeguard your business. With the right legal strategy, you can challenge, renegotiate, or enforce liquidated damages in your favor.
Take action today—don’t let a contract clause threaten your business. Contact Southron Firm, P.A. to schedule a consultation. We’ll review your contract, explain your options, and fight for the best possible outcome for your business.
Facing a liquidated damages claim? Let our attorneys fight for your business.

